Redwood Shores' Lab Campus Plan Will Move on Paper Long Before It Breaks Ground

North of the Redwood Shores lagoon, between Marine Parkway and Belmont Slough, sits a 1990s office park of 20 two-story buildings surrounded by surface parking. Its address range runs from 800 to 3400 Bridge Parkway, and it holds about 970,000 square feet of offices on roughly 84 acres. Its owner, Longfellow Real Estate Partners, wants to replace it with a 2.73-million-square-foot life sciences campus called Redwood LIFE.

The next steps for that proposal are documents. Once the Draft Environmental Impact Report comes out, the public gets 45 days to respond, and a Planning Commission hearing near the end of that window takes comments. The city's FAQ projects plan adoption in early 2027. Any construction comes later, in phases, and in a lab market that is still working through a large surplus.

The 45-day window is the date that matters

In July 2026, the city's project site said the Draft Precise Plan and Draft EIR had "taken longer than originally anticipated." It expected to publish both "in late summer or early fall," with a community meeting early in the 45-day review period and a joint City Council and Planning Commission study session to follow. The November 2026 issue of The PILOT, the Redwood Shores Community Association's monthly publication, reported that RSCA still had no information on when the EIR would come out. It described the release as "a whirlwind process, since only 45 days are allowed for responses."

Here is the order of events as the city has laid it out:

  1. The Draft Precise Plan and Draft EIR are published, and the city notifies residents by email, social media and updates to PlanRedwoodLife.org.
  2. City staff hold a community meeting early in the 45-day review period.
  3. The Planning Commission takes public comments near the end of that period.
  4. The City Council and Planning Commission meet in a joint study session.
  5. The city considers repealing the 1995 Westport Specific Plan and replacing it with a new Redwood LIFE Precise Plan. Its FAQ estimates adoption in early 2027.

Step five is where the stakes are. The city calls Longfellow's proposal consistent with the General Plan but larger than the existing Westport Specific Plan's standards allow. According to the city, the new Precise Plan will set land-use, site-design, circulation, infrastructure and open-space standards for the site.

What the plan would replace

The city's project page describes the current application this way:

Today Proposed
Buildings 20, office 12, on five reconfigured parcels
Floor area About 970,000 sq ft 2,731,280 sq ft of R&D, 1.76M sq ft net new
Hotel None 104 rooms, 102,620 sq ft
Community amenity center None About 20,000 sq ft
Open space 4.6 acres public, per 2025 reporting 42.4 acres, 38.7 privately owned and publicly accessible
Parking 3,400 spaces, per 2025 reporting 5,773 joint public/private, plus 646 bike spaces
Construction None Seven phases

The current application has no housing. It is also smaller than earlier versions. A previous HOK design called for 13 buildings between 55 and 100 feet tall, totaling 3.1 million square feet, as The Real Deal reported. In April 2025, the City Council chose a scaled-back Alternative 2 to study in the EIR. The council noted that the vote was not a project approval, and Longfellow's revised 2025 application follows that alternative.

At a February 2025 city workshop, preliminary figures showed how Alternative 2 changes the edge closest to homes. Under the original proposal, buildings averaged 135 feet from the site's southeast property line and sat about 80 to 100 feet from the Slough. Alternative 2 moved them to an average of 270 feet and about 160 feet. The workshop also showed massing that stepped down from six stories to five near the neighborhood. It moved an internal road, Longfellow Lane, and parking away from homes. These are early design figures. The Draft Precise Plan is the document that will set the actual numbers.

Why approval and construction are on different clocks

The lab market explains why the gap between plan adoption and groundbreaking could be long.

As of Q3 2026, Savills put Bay Area life sciences vacancy at 23.8%, with 9.9 million square feet available. Its same report shows venture funding for the quarter at $2.6 billion, compared with $4.8 billion a year earlier. Cushman & Wakefield's Q2 2026 figures put San Mateo County lab vacancy at 30.7%. Colliers, which tracks the broader R&D category, reported 22.6% vacancy and 28.6% total availability for Redwood City and Redwood Shores in Q2 2026. Each firm defines its market differently, but all three show roughly a quarter or more of the space empty.

The developer has said openly that it is betting on a recovery. In March 2025, The Real Deal reported that Longfellow and its partner PGIM were betting on a life sciences rebound within five years. It quoted Longfellow managing director Peter Fritz: "Everyone's read the headlines about the supply and demand of life sciences in the Bay Area, but we are very bullish." The same report said that, pending approvals, the project could break ground in five years at the earliest. In September 2026, a San Francisco Business Times headline listed Longfellow among developers whose Bay Area biotech projects had been turned over to lenders. The article's preview said many newly added projects were sitting vacant and lenders were calling in loans.

So the timeline has two separate parts. Approval could come in 2027. Groundbreaking, on the developer's own 2025 estimate, could not come before about 2030. After that, the work proceeds in seven phases. In the meantime, the existing campus is still in use. Life sciences companies there have included Nevro, Procept BioRobotics and Jasper Therapeutics, and the campus leasing site lists fitted lab and office suites available now.

What neighbors have put on the record

Because construction is far off and phased, the formal objections focus on the long term. RSCA's 2026 petition opposes the project. It raises:

  • Taller buildings closer to homes
  • Congestion on Redwood Shores routes, Ralston Avenue and Highway 101
  • Capacity of emergency services
  • The balance between jobs and housing
  • More than 25 years of phased construction
  • Building on the former Westport Landfill

A letter from Sierra Club Loma Prieta, Bird Alliance and Green Foothills asked the city to study the combined effects of construction, traffic and noise. It also asked the city to keep Bay Trail access continuous, and it pointed out that most of the planned open space would stay privately owned. These are objections, and the Draft EIR is the document meant to analyze them. A February 2025 city workshop listed Bay Trail enhancements among the proposed community amenities.

For a buyer comparing the Shores with Belmont or San Carlos, the practical result is this. Homes near Marine Parkway are next to a site whose long-term form goes to public review once the Draft EIR is out, and whose construction would stretch over many years after any approval. The Draft Precise Plan is where the setbacks, heights and access for that site will appear in writing.

Frequently asked questions

Is any housing part of Redwood LIFE? Not in the current application. Longfellow's 2022 concept included off-campus housing and an $85 million affordable housing contribution. Those items belonged to that earlier plan and are not in the version under review.

How will I hear when the Draft EIR is released? The city says it will announce the release by email, on social media and on PlanRedwoodLife.org. RSCA also covers the project in The PILOT, which it says reaches 6,000 Shores households and businesses each month.

Is the site a former landfill? Yes. Materials from a city-hosted information session identify it as the Westport Landfill. They say its cap was rebuilt in 1995–1996 and that groundwater monitoring and landfill-gas inspections are ongoing.

If you own a home near Marine Parkway and want to know how buyers are likely to weigh the Redwood LIFE timeline when they look at your property, Marylene Notarianni can prepare a valuation that factors in the plan's current stage. Request a free home valuation, and we'll walk you through it in plain terms.